| Geomaterial |
Applied Energy (ton-m/m2) |
Depth of Improvement (m) |
| Loose building waste | 150 | 4 |
| Ash fill | 150 | 3.5 |
| Select granular fill | 150 | 4 |
| Sandy silt | 80 | 2 |
| Silty sand | 190 | 3 |
| Geomaterial |
SPT N Value after Improvement |
Typical improvement Depth (m) |
| Sand | 20-30 | 6 |
| Silty sand | 15 | 4.5 |
| Sandy silt | 10-15 | 3.5-4.5 |
| Uncontrolled fill | >10 | 3 to 5 |
Geotechnical Design and Solution Ground Improvement Deep Foundation Earth Retention Grouting Technology Injection System Excavation and Stablization Seepage Control Slope Stabilisation Rapid Impact Compaction Deep Soil Mixing Micropile Shotcrete Anchor and Soil Nail Diaphragm Wall Secant Piles Wall Deep Dynamic Compaction Rock fall and avalanche Barrier Sheet pile wall
Top-down method is a rapid method which enables builders to construct the substructure and superstructure simultaneously. Likewise it is used as an excavation stabilization method in cases where you can’t or you are not allowed to use the other geotechnical methods such as soil nailing and soil anchorage.
Diaphragm walls are continues adjacent concrete walls to reduce mainly the underground water seepage and apart of engineering load-bearing elements to stabilize deep excavations with a strong vertical facing.
Sheet pile walls are usually installed to support temporarily or permanently the excavations in unstable soils. In large depth the sheet piles are usually supported from lateral movements by anchorage or reciprocal supports.